#81862: "Contracts"
O čom je toto hlásenie?
Čo sa stalo? Prosím vyber z nasledujúcich
Čo sa stalo? Prosím vyber z nasledujúcich
Prosím skontroluj, či už existuje hlásenie na rovnakú tému
Ak je to tak, prosím HLASUJTE za toto hlásenie. Hlásenia s najviac hlasmi majú PRIORITU!
| # | Status | Votes | Game | Type | Title | Last update |
|---|
Podrobný popis
-
• Prosím skopíruj a vlož chybové hlásenie, ktoré si videl na obrazovke, ak sa nejaké vyskytlo.
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). -
• Prosím vysvetli, čo si chcel/a spraviť, čo si spravil/a a čo sa stalo
Move #359
I fulfilled a contract and the dam construction on it was taken automatically because there was only one available space and I had the 3 Credits needed for that space.
I should be able to choose not to construct that dam (I may want to fulfill the contract for it to count for a bonus tile, without being interested by a dam on that position). • Aký prehliadač používaš?
Google Chrome v109
-
• Skopíruj/vlož text zobrazený v angličtine namiesto tvojho jazyka. Ak máš screenshot (dobrý zvyk), môžeš použiť Imgur.com na jeho nahranie a skopírovať sem odkaz na neho.
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). -
• Je tento text dostupný v prekladovom systéme? Ak áno, bol preložený po dlhšie ako 24 hodín?
Move #359
I fulfilled a contract and the dam construction on it was taken automatically because there was only one available space and I had the 3 Credits needed for that space.
I should be able to choose not to construct that dam (I may want to fulfill the contract for it to count for a bonus tile, without being interested by a dam on that position). • Aký prehliadač používaš?
Google Chrome v109
-
• Prosím presne a stručne vysvetli svoj podnet, aby bolo čo najjednoduchšie pochopiť, ako to myslíš.
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). • Aký prehliadač používaš?
Google Chrome v109
-
• Čo sa objavilo na obrazovke, keď si bol zablokovaný (Prázdna obrazovka? Časť herného rozhrania? Chybové hlásenie?)?
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). • Aký prehliadač používaš?
Google Chrome v109
-
• Ktorá časť pravidiel nebola dodržaná v BGA adaptácii?
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). -
• Je možné vidieť porušenie pravidiel na zázname z hry? Ak áno, aké je číslo ťahu?
Move #359
I fulfilled a contract and the dam construction on it was taken automatically because there was only one available space and I had the 3 Credits needed for that space.
I should be able to choose not to construct that dam (I may want to fulfill the contract for it to count for a bonus tile, without being interested by a dam on that position). • Aký prehliadač používaš?
Google Chrome v109
-
• Aký herný ťah si chcel urobiť?
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). -
• Čo si skúsil aby si vyvolal túto akciu?
Move #359
I fulfilled a contract and the dam construction on it was taken automatically because there was only one available space and I had the 3 Credits needed for that space.
I should be able to choose not to construct that dam (I may want to fulfill the contract for it to count for a bonus tile, without being interested by a dam on that position). -
• Čo sa stalo keď si spravil túto hernú akciu (chybové hlásenie, hlásenie v stavovom pruhu, ...)?
• Aký prehliadač používaš?
Google Chrome v109
-
• Kedy v priebehu hry sa problém vyskytol (aká bola prebiehajúca herná inštrukcia)?
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). -
• Čo sa stalo keď si spravil túto hernú akciu (chybové hlásenie, hlásenie v stavovom pruhu, ...)?
Move #359
I fulfilled a contract and the dam construction on it was taken automatically because there was only one available space and I had the 3 Credits needed for that space.
I should be able to choose not to construct that dam (I may want to fulfill the contract for it to count for a bonus tile, without being interested by a dam on that position). • Aký prehliadač používaš?
Google Chrome v109
-
• Prosím popíš viditeľný problém. Ak máš screenshot (dobrý zvyk), môžeš použiť Imgur.com na jeho nahranie a skopírovať sem odkaz na neho.
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). • Aký prehliadač používaš?
Google Chrome v109
-
• Skopíruj/vlož text zobrazený v angličtine namiesto tvojho jazyka. Ak máš screenshot (dobrý zvyk), môžeš použiť Imgur.com na jeho nahranie a skopírovať sem odkaz na neho.
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). -
• Je tento text dostupný v prekladovom systéme? Ak áno, bol preložený po dlhšie ako 24 hodín?
Move #359
I fulfilled a contract and the dam construction on it was taken automatically because there was only one available space and I had the 3 Credits needed for that space.
I should be able to choose not to construct that dam (I may want to fulfill the contract for it to count for a bonus tile, without being interested by a dam on that position). • Aký prehliadač používaš?
Google Chrome v109
-
• Prosím presne a stručne vysvetli svoj podnet, aby bolo čo najjednoduchšie pochopiť, ako to myslíš.
Contracts rewards are not mandatory (boardgamegeek.com/thread/2241819/article/32509710#32509710),
except for energy (boardgamegeek.com/thread/2184487/article/31754910#31754910). • Aký prehliadač používaš?
Google Chrome v109
História hlásenia
The elevation granted by the contract was automatically build because there was only one place available.
Contract rewards are not mandatory.
The conduit granted by the contract was automatically built.
When there isn't only one place available, there is an option to skip building the structure. It should always be an option.
Pridať niečo k tomuto hláseniu
- Iné ID stola / ID ťahu
- Vyriešil sa problém pomocou F5?
- Objavil sa problém viackrát? Zakaždým? Náhodne?
- Ak máš screenshot (dobrý zvyk), môžeš použiť Imgur.com na jeho nahranie a skopírovať sem odkaz na neho.